Lordscairnie
1 turbine | 45.7m to blade tip | 225kW
Lordscairnie was developed in partnership with Temporis Wind and granted planning permission in April 2012.
Lomond Energy managed the project from feasibility, through design & planning application to permission, prior to handing over to Temporis Wind for financing and construction.
During the planning application phase an SNH (now NatureScot) objection in regard to wintering geese was overcome through the commissioning of a winter bird survey which demonstrated that the turbine would not present any significant risk to the geese.
Key facts
Location
Lordscairnie, Moonzie, near Cupar, Fife
Status
Operating since 2013
Benefits
- New income stream for local farm underpinning its long term future
- 516,000 units of carbon-free electricity annually, equivalent to the consumption of around 126 homes
Structure
Development partnership with Temporis Wind